Assignment 04
BZ460 Project Management
Directions: Be sure to make an electronic copy of your answer before submitting it to Ashworth College for grading. Unless otherwise stated, answer in complete sentences, and be sure to use correct English spelling and grammar. Sources must be cited in APA format. Refer to the "Assignment Format" page for specific format requirements.
Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project. Can the project be completed in 40 weeks? Assume that Activity A actually finished at 3 weeks, Activity B actually finished at 12 weeks, and Activity C actually finished at 13 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?